Sky News has reported that National Grid has struck a deal paving the way for Britain’s biggest electricity substation to be built on Teesside as the government races to avoid missing out on global demand for AI infrastructure development.
Where will the substation be built?
Last Week, National Grid Electricity Transmission (NGET) signed a deal to purchase more than 70 acres of land at Dorman Point on a site owned by Teesworks Ltd, in order to build the new substation. The publicly owned South Tees Development Corporation (STDC) owns most of the land at Dorman Point, apart from a small portion owned by Teesworks. It’s possible that Teesworks purchased the 70 acres of Dorman Point from the STDC at some stage, then sold it to NGET.
Steel River Power
Sky News confirmed that Balfour Beatty, the London-listed infrastructure services group, was in line to deliver the Teesworks substation for National Grid, in partnership with Steel River Power (SRP), which owns and operates the private electricity network across the estate.
Who owns what?
Teesworks Ltd is 90% owned by four Joint Venture Partners. Of these, Chris Musgrave and Martin Corney own the majority of the company between them. Ian Waller and Christopher Harrison own the remaining stakes. Steel River Power is a joint venture between Steel River Energy Limited (SREL) and North West Electricity Networks, part of the energy giant Iberdrola, which owns the UK supplier Scottish Power. Chris Musgrave and Martin Corney each hold a 45% stake in SREL. The STDC holds the remaining 10% stake.
Data centre
North East Bylines will recall our June 2026 report on how Teesworks Ltd bought 220 acres of land at the former Redcar Steelworks site for £1 an acre, then sold it to Anthropic for £1mn an acre. Balfour Beatty’s contract will also include the construction of a high-voltage connection between the new substation and the Anthropic data centre site, which are about three miles apart.
The Foundry Site
The data centre will occupy the Foundry Site at Redcar. The remains of the former Redcar Blast Furnace remain in situ, despite the main structure having been demolished four years ago. This “stump” of solid iron has proved highly problematic to remove. The Royal Engineers were consulted about removing the furnace with high explosives, but they considered it Mission: Impossible. In May 2024, STDC hired a company called Precision Engineering to finish the task. It engineered precisely nothing.
Power supply problem
However, even when the new Dorman Point substation is in place, there will still be a problem in supplying dispatchable, or “baseload” supply to the data centre. Dispatchable/baseload electricity is power “on demand”. Data centres need dispatchable power because they need to run 24/7. Renewable energy is intermittent, ie the sun has to shine or the wind has to blow.
So, where do we get dispatchable power from?
A quick explainer: One Megawatt (MW) is a Thousand Watts. One Gigawatt (GW) is a Million Watts.
Now that there is no coal-fired electricity supply in the UK, this dispatchable power has to come from nuclear or gas. In addition to its new substation contract, Balfour Beatty is also building the Net Zero Teesside (NZT) gas-fired power station, which should come onstream in about five years time. That will be able to supply 742 MW (0.742GW) of electricity. The UK Government has just stipulated that all new gas-fired power stations must be connected to the National Grid. However NZT may avoid this stipulation, and it could be harnessed to exclusively power the new Anthropic data centre next door.
Can anybody else chip in?
But the data centre will need 3.2GW of power, so NZT would only be able to provide less than a quarter of the power required. Anthropic could maybe call on Hartlepool nuclear power station, which could supply 1.2GW, to get a third of its data centre online. However, most of Hartlepool’s electricity is needed to supply the national grid. The station has had several lifetime extensions, and is coming to the end of its useful life. It is currently licenced to operate until March 2030.
Battery Energy Storage Systems
Renewable electricity supply can be evened out with battery storage, but there’s not much of this available. A company called NatPower plans to build four Battery Energy Storage Systems (BESS) in the region called “Gigaparks” because they would be able to supply a Gigawatt (GW) of energy on demand. That is, until the battery runs out. But none of the NatPower gigaparks has been promised a grid connection yet.
Electricity network map
The map below shows the projected electricity network in the Tees Valley in 2031. The four proposed Gigapark BESS are shown in green on the map. Each of these is proposed to have a storage capacity of 1GW each. The gigaparks are, from north to south, Hawthorn, Teesside, Mowbray, and Bellmoor. There is no guarantee that any of the gigaparks will ever be built.

Small scale BESS
There’s a small scale 150 MW BESS at Wilton, with another 100 MW facility, by a company called EOS supposedly on the way at Teesworks. But despite a press release, we’ve heard nothing from EOS since December 2024. So Teesside doesn’t have much battery capacity to even out supply when dispatchable power isn’t available.
Renewables
The 2031 map above shows that Teesside will have plenty of renewable electricity available soon. There’ll be 2.6GW available from Dogger Bank to the east, and another 2GW via the Eastern Green Link from Torness, which is about 30 miles east of Edinburgh. Only when the wind is blowing. Teesside has the Redcar Array, which would be just opposite the new data centre if it was ever built. But the Redcar Array only supplies 62 MW at full tilt, which is insignificant in terms of data centres.
Is Artificial Intelligence junk?
The Financial Times has reported that Anthopic may soon be given a “junk” credit rating following its recent Initial Public Offering. Will Anthropic follow a long line of Teesworks “investors” which turn to junk? Only time will tell.
More rubbish
The new Dorman Point Electricity Substation will be built next door to the Grangetown Monster Incinerator, also known as Tees Valley Energy Recovery Facility (TVERF). A reminder that TVERF, in addition to burning the waste of all local authorities in the Tees Valley, will also burn the trash from County Durham and the City of Newcastle. And, as soon as it starts operating, we’re all stuck with a 29-year contract.
Will the lights stay on?
If built, the substation would beef up the electricity grid in Teesside. But substations don’t supply electricity, they only convey it. Keep in mind that the new Redcar data centre, if built, would gobble up 3.2 GW of electricity, enough to power about 3.5 million homes. That’s three times as many as in the entire North East of England. If your lights suddenly start to dim, you’ll know there’s an issue.
Comfort food
Assuming that we ever get to the day of the big data centre switch-on, make sure you’ve taken the recent government advice, and stocked up on loads of tinned food and pasta.
Thanks to James Waterson for providing additional research for this article.

Friends of Bylines Network
There has never been a greater need for grassroots journalism that investigates the stories that really matter, holds power to account and champions the voices of everyday citizens. We are proudly powered by volunteers but what we do isn’t free.
STAND WITH US for independent, citizen-led journalism that makes democracy stronger, and you will even get some exclusive benefits.