So, BP finally made it official. After months of rumours, the company confirmed that it is calling it quits on both of its Teesside hydrogen projects.
Green, blue, whatever
BP walked away from HyGreen, its green hydrogen project, in March 2025. On 2 December, the company confirmed that the neighbouring blue hydrogen project, H2Teesside, would be cancelled. This should pave the way, instead, for a data centre to be built by Google.
Nationally Significant Infrastructure Project (NSIP)
Because H2Teesside was a NSIP, it was down to Energy Secretary Ed Miliband to grant a Development Consent Order (DCO). Miliband delayed his decision on the DCO twice, on 28 August, and then again on 30 October. It should have been third time lucky on 4 December. But the Energy Secretary took a gamble on BP’s patience wearing thin. That proved to be a good call for Ed, as he’s avoided an upcoming banana skin.
Compulsory Purchase
If BP had been granted a DCO, this would have included power to compulsorily purchase land at the former Redcar steelworks. That would have been kryptonite to the Teesworks joint venture partners, Martin Corney and Chris Musgrave.
South Tees Group
The BBC reported that “the project, H2Teesside, had been mired in controversy after landowners South Tees Group (STG) sought permission to build a data centre there instead” However, the STG isn’t the landowner. The STG is merely an umbrella group for Teesworks Limited and the South Tees Development Corporation (STDC). The land is owned by yet another related company, the South Tees Site Company (STSC).
Have we seen this movie before?
So will Teesworks Limited buy the data centre land plot from the STSC? And will it pay more than £1 per acre? Here’s a chilling excerpt from the independent review of the Teesworks Joint Venture, also known as the Tees Valley Review.

It’s all about timing
The data centre land plot hasn’t been remediated yet. A £13.2mn tender for remediation of the site, known as Foundry Central West, was issued in May 2025. This remediation is being publicly funded via the Tees Valley Combined Authority (TVCA) on behalf of the STDC. See how this works? The Tees Valley Review noted that “at this juncture, the (Teesworks) joint venture partners have put no direct cash into the project and have received nearly £45mn in dividends and payments, and hold £63mn of cash from the SeAH income strip in TWL accounts.”
Tees Green Hydrogen
The Department for Energy Security and Net Zero (DESNZ) said the decision to pull out had been made by BP. “We continue to provide a route for hydrogen projects in Teesside, including Tees Green Hydrogen (TGH), which is moving towards final investment decision, along with several other projects creating high-quality jobs for the region,” a spokesperson said.
Power Play
But TGH isn’t a major project. It was announced two years ago by EDF, with a plan to start construction in 2025. That isn’t going to happen. The plant, if built, will be puny, with a capacity of only 7.5 megawatts. By comparison, the nearby NZT Power is planned to generate almost 100 times as much, at 742 megawatts. TGH will rely on surplus electricity from EDF’s Teesside Wind Farm. However, the wind farm needs to supply the national grid as a first priority.
Social media
Tees Valley Mayor Ben Houchen took to social media to crow about BP’s decision:

That was a bold statement. Let’s unpack it:
“The biggest private investment Teesside has ever seen”
Teesside wasn’t even mentioned in the government’s announcement on 24 September about the North East AI Growth Zone. Ben Houchen had jumped the gun 13 days earlier, claiming that Teesside would be included.
“BP’s challenges”
The main one of which was Ben Houchen’s cronies, the Teesworks joint venture partners, planning a data centre on the same land that they had promised BP for its hydrogen project. Teesworks applied for outline permission for a data centre in March 2021. More on that here.
“We’ll continue working with BP to deliver NZT”
The Net Zero Teesside (NZT) project is going ahead, as part of the wider Northern Endurance Partnership (NEP) carbon capture project. Balfour Beatty, the main contractor, started work in July. But NEP is a 3-way joint venture between BP, Equinor and Total Energies. After being on the receiving end of numerous letters from the STG’s lawyers, BP execs may decide that they don’t need the Teesside aggravation, and could sell up to Equinor and Total.
“Land on the former steelworks is limited”
That’s odd, because Ben Houchen has spent the past eight years banging on about Teesworks being “the largest brownfield site in Europe”. What suddenly happened to all of this land? The truth is that this was always a myth. When you disregard “undevelopable” land such as landfill sites, and other land that hasn’t been remediated, there’s very little available. Also, the available plots are scattered in patches throughout south Teesside. You can read a more detailed breakdown of the available land here.
Why hasn’t more land been remediated?
Despite a public sector investment of £560mn in Teesworks, only 450 acres of land has been remediated. This consists of the new quay and SeAH factory at South Bank, and the NZT Redcar site. It’s a stark contrast to the 4,500 acres that Teesworks frequently boasts about.
Searching in vain
In August, Ed Miliband asked STG’s lawyers to provide evidence that another plot of land at Teesworks could be used for their AI data centre. The lawyers had no incentive to do this, and they didn’t. The former Redcar steelworks site, part of Teesworks’ “Foundry Zone”, is the only game in town.
“A cutting edge data centre will create more long-term jobs”
It won’t. Apart from the construction phase, data centres don’t create jobs. It’s worth noting that BP had promised 1,400 construction jobs on the H2Teesside project.
Private Wire Network
And so, assuming that Google is still interested after all of these shenanigans, the AI data centre will go ahead. Electricity for the power-hungry centre will be supplied via Steel River Power Limited (SRPL). The largest shareholders in SRPL are, of course, the two Teesworks joint venture partners.
But where will the power come from?
Plans to sell expensive electricity will founder if there isn’t any to sell. Where will SRPL get its electricity from? Due to a gas turbine supply crunch, the new neighbour NZT Power is probably six or seven years away.
Data centres are thirsty too
At the most recent meeting of the STDC Board on 11 September, the Chief Executive John Barnes noted that “the long-term planning for the expansion of the Private Water Network, fully funded by the private sector, was approved at a previous meeting. This plan aligns with tenant requirements and ensures compliance with NWL and Ofwat guidelines. Following this approval, initial water offers have been issued to, and signed by, several tenants across the site”
Private Water Network
Unlike the Private Wire Network, a private water company hasn’t been registered at Companies House yet. Machinery and operatives from TCC Plant Ltd have been seen renewing the water main that crosses Coatham Marsh, linking the external Northumbrian Water supply to the former Redcar steelworks site. Martin Corney’s son Chester is a co-director of TCC Plant Ltd.
The Spectator
The climate-deniers at the Spectator reported BP’s Teesside decision as “The day net zero died”, no less. This is a complete misrepresentation of blue hydrogen, which was always going to be a blind alley on the way to decarbonization. However, the Spectator has a point. The electricity and water requirements of AI data centres will prove to be disastrous for net zero targets.
Is this the end of Houchen’s hydrogen hype?
Well, not quite. He’s still got the above-mentioned TGH to hang on to. And a company called Kellas is supposed to be developing another blue hydrogen project, H2NorthEast, at Seal Sands, on the other side of the river from Redcar. This project is a slow burner though. It was first announced more than four years ago. Coincidentally, this was about the same time that BP announced the ill-fated H2Teesside.
Hydrogen filling station
There’ll be a hydrogen filling station at the Teesside Airport too. Drivers will need to be patient though. There hasn’t been much progress since this was announced in August 2023. But the Europeans are ahead of the UK yet again. They’ve already realised that hydrogen vehicles are never going to work, and are busy shutting down the hydrogen filling station network.
Thanks to James Waterson for contributing to this article